The localization of defected fuel assembly requires power reduction at Olkiluoto 1
28.11.2026
Work requiring a power reduction will be carried out at Olkiluoto 1 (OL1) starting on Monday, 30 November 2026, to locate a defected fuel assembly and to take the necessary measures.
The defect will be located and the necessary measures carried out on Monday morning at a reduced power level of approximately 465 MW, without interrupting electricity production. The plant unit will then be returned to full production power. The work is estimated to take approximately two days.
Periodic tests requiring a power reduction will also be carried out during the power restriction.
The issue has no impact on nuclear safety.
More detailed information on the schedule is available on the Nord Pool electricity market platform: https://umm.nordpoolgroup.com