Olkiluoto 3 Maintenance Outage Completed

17.11.2026

The Olkiluoto 3 maintenance outage has been completed, and the plant was reconnected to the national power grid on Tuesday, 17 November, at 5:16 p.m. The ramp-up to full power will take approximately 80 hours. OL3 will now begin an operating cycle of approximately 18 months before its next scheduled maintenance outage.


The OL3 maintenance outage began on 10 September and lasted a total of 68 days. More than 2,000 jobs and 6,000 work packages were completed during the outage. The most significant work included refueling and fuel inspections, maintenance and inspections of the main coolant pumps, and maintenance of electrical switchgear. Pump faults that had previously affected the plant’s electrical output were also repaired during the outage.

The outage lasted longer than originally planned due to findings made during inspections and the resulting need for additional repairs. Additional work was carried out on components including valves where inspections had identified wear. The necessary repairs were completed thoroughly before restarting the plant for its next operating cycle.

- This was my first OL3 maintenance outage in my new role, and I was particularly impressed by the strong commitment and professionalism of our own personnel. Together with our partners, we completed this extensive undertaking safely and to a high standard, providing a solid foundation for reliable electricity generation at OL3 over the next 18 months, says TVO’s Senior Vice President of Maintenance, Marko Kesti.

Lessons Learned from Operational Events Will Be Applied to Future Outages

Deviations were also identified during the maintenance outage, and TVO has prepared or is preparing the necessary reports for the Finnish Radiation and Nuclear Safety Authority (STUK). The events were related to matters including the plant shutdown, system testing, and the execution of maintenance work.

TVO is investigating the causes of the events and will determine the necessary improvement measures based on the findings. Particular attention will be paid to the management of maintenance work, the management of equipment and system isolations and restorations, and careful planning of work.