OL3 to resume electricity production earlier than expected
Olkiluoto 3 will resume electricity production today, Thursday, 26 November, at around noon. The investigation and repair work at the plant unit was completed ahead of the original schedule.
Electricity production at OL3 was interrupted on Thursday, 26 November, at 4:15 AM to investigate and repair a valve defect in a process system. According to the original estimate, the investigation and repair work was expected to be completed by Saturday evening.
The valve defect was detected last Friday when the plant unit was increasing power following the outage. On Wednesday, 25 November, OL3's power output was reduced to approximately 60 per cent to investigate the defect. The investigations determined that the valve defect could not be repaired while the plant unit was operating at this reduced power level, and electricity production was therefore interrupted.
The teams worked intensively to investigate and repair the defect, and through good cooperation, the work was completed ahead of the original schedule.
The Olkiluoto 1 and Olkiluoto 2 plant units have produced electricity normally throughout the OL3 production interruption.
More detailed information on the schedule is available on the Nord Pool electricity market platform: https://umm.nordpoolgroup.com