Olkiluoto 3 Annual Outage to Be Completed Already by the End of April
The annual outage of OL3, which began on March 1, has progressed smoothly. According to the current estimate, electricity production at the plant unit can resume by 28[th] of April. Originally, the outage was scheduled to be completed in early May.
The scheduling of Olkiluoto’s annual outage was based not only on experience from previous outages but also on preparations for potential unforeseen repairs. The ongoing outage at OL3 has so far avoided major surprises that could affect the timeline, and the planned tasks have proceeded well. The most extensive work has now been completed, and the next step involves carrying out a few final preparatory tasks to enable the restart of the plant and the resumption of electricity production.
More detailed information on scheduling is available on the Nordpool electricity market platform: https://umm.nordpoolgroup.com