“Annual outage lays foundation for safe and uninterrupted operation of nuclear power plant”

21.3.2024

The annual outage of the Olkiluoto 3 plant unit started in early March with the disconnection of the plant from the national grid. Jukka Kallionpää works as the on-site inspector and representative for the Radiation and Nuclear Safety Authority (STUK) in Olkiluoto and he, too, plays an important role during annual outages.

As a representative of the regulatory body, Kallionpää sums up concisely the significance of annual outages.

- The annual outage is the stone foundation for the operation of the nuclear power plant. During the outage, part of the fuel is replaced in the reactor, the safety of the plant is verified, and activities are carried out to assure that the plant will produce electricity without disruptions as far as possible until the next service outage.

Kallionpää, who has worked in Olkiluoto since 2009 as STUK’s on-site inspector, has followed closely TVO’s preparations for the annual outages and is also invited to the meetings where maintenance activities are planned.

- The on-site inspector’s role is important also toward the end of the annual outage when the reactor cover is closed and preparations made for the reactor startup. Both actions are subject to permission from the regulatory authority, STUK.

The service outage of OL3 is different from the outages of OL1 and OL2

Kallionpää stresses that the maintenance programme for OL3 is different from that at the OL1 and OL2 power plant units. With a net electrical output of about 1,600 MW, OL3 is considerably larger than the 890 MW plant units OL1 and OL2.

- The number of components and the size of the plant give it a larger scale. OL3 is also structurally different. It is a pressurised water reactor of EPR type, whereas OL1 and OL2 are boiling water reactors. This results in a different maintenance programme.

At the OL1 and OL2 plant units, the outages are carried out in alternate years as a shorter refuelling outage or a longer service outage (includes also refuelling). The slower shutdown procedure of the EPR plant compared to the two older plant units impacts the duration of the service outage at OL3. The turbine plant is slower to cool down and the reduction of the higher reactor output in compliance with a specific output curve takes more time.

- The service outage of this spring is the first one, which means that a large number of various inspections and analyses are carried out at the plant to establish the mechanical impacts after one year of operation. In addition, warranty inspections are conducted during the first annual outage with representatives of the plant supplier present, Kallionpää says.

Safety comes first - always

Oversight Manager Essi Vanhanen from STUK is in charge of all the oversight activities at the Olkiluoto 3 plant unit. She has the overall picture of everything observed and reported by the dozens of STUK’s experts about the operation of OL3.

- The task of STUK’s representatives is to ensure that the operation of the plant is safe. STUK also wants to verify that the activities associated with the first service outage at OL3 are carried out prioritising safety, Vanhanen emphasises.

The annual outage of OL3 is overseen by several experts from STUK.


Essi Van­hanen

- Our inspectors reviewed all safety-related plans already before the start of the service outage. I myself visit the plant on a regular basis, as you need to be at the plant to get the best picture of the activities.

According to Vanhanen, the first annual outage of OL3 is used to build functioning practices for subsequent annual outages.

- With a new nuclear facility, there are no routines in place for the annual outage such as have been created for the maintenance of older plant units over the decades. From the point of view of the authority, the essential aspect is to be able to witness on site that work is carried out in a systematic manner. We do not pay attention to the schedule of the outage, but to everything being done safely, Vanhanen stresses.

The Oversight Manager particularly emphasises radiation protection as a special feature of nuclear plants.

- The measures for radiation protection are designed to keep the radiation doses of the personnel within safe limits. This distinguishes maintenance work carried out at a nuclear power plant from other power plants.

A plethora of rooms

The first commercial operating cycle of Olkiluoto 3 was relatively free from disruptions considering that technical challenges are often encountered in the commissioning of a new power plant.

- The first operating cycle was successful, which was no doubt the result of extensive tests and the test production phase.

The annual outage involves a high number of mechanical inspections at the plant to verify that the equipment and components are failure free and operable. STUK also participates in these inspections.

- With the completion of the first annual outage, the plant will be well equipped for secure production of electricity during the next operating cycle.

OL3 has some 3,000 rooms. Vanhanen is often accompanied by TVO’s personnel or STUK’s on-site inspectors at the plant, but says she has already learned the most important routes.

- Sometimes I seem to take a slightly longer route, if I go to the plant by myself, she smiles.



Text: Timo Sillanpää