Annual outage of Olkiluoto 1 plant unit is completed
The 44th annual outage of Olkiluoto 1 (OL1) plant unit is now completed.
In addition to fuel replacement, the annual maintenance and testing were performed during the fuel change outage. Significant individual tasks included replacement of the SIRM detector and the swamp tube, modernization of the turbine hall crane and oil change for the turbine.
In addition to the staff, approximately 700 subcontractors participated in the maintenance. Almost 600 work permits were applied for and returned to the work permit office and a total of about 700 separate work tasks were performed at the plant.
OL1 returned to electricity production on Wednesday 26 April at 8:56 PM. The duration of the annual outage thus became 10 days, 2 hours and 56 minutes.
The maintenance outage to be carried out at Olkiluoto 2 (OL2) starts on Monday, 1 May. The duration of this outage is 16 days.