Teollisuuden Voima Oyj Interim Report January–March 2021

22.4.2021

During the first quarter of 2021, Teollisuuden Voima’s (TVO) electricity generation at the Olkiluoto 1 (OL1) and Olkiluoto 2 (OL2) plant units continued safely and reliably.

The Radiation and Nuclear Safety Authority (STUK) granted a fuel loading permit for the Olkiluoto 3 EPR plant unit (OL3 EPR) on March 26, 2021. The fuel loading was started on March 27, 2021. According to the schedule TVO received from the plant supplier Areva−Siemens consortium in August 2020, the OL3 EPR plant unit will be connected to the grid in October 2021, and regular electricity production starts in February 2022.

The construction work at Posiva’s encapsulation plant and final disposal facility has proceeded as planned.

The TVO Group has taken extensive measures to prevent the spread of coronavirus (COVID-19) infections. Despite of COVID-19 restrictions, work has been able to continue under special arrangements.

Please find the full Interim Report January–March 2021 on tvo.fi web pages.