OL3 EPR regular production of electricity starts in February 2022

28.8.2020

Teollisuuden Voima Oyj (TVO) has received an updated re-baseline schedule on the commissioning of the OL3 EPR plant unit from the supplier Areva-Siemens consortium. According to the schedule fuel will be loaded into the reactor in March 2021, the unit will be connected to the grid in October of the same year, and regular electricity production starts in February 2022.