Supplier confirms delay in the execution of Olkiluoto 3
25.1.2006
The Supplier of the Olkiluoto 3 nuclear power plant unit, a consortium comprising Framatome ANP and Siemens, confirms that the reactor building civil works and the manufacture of certain primary components are delayed as compared to the original schedule.