Works Continue at Olkiluoto 3 Construction Site
- We were surprised to read the information Areva released, says Jarmo Tanhua, President and CEO of TVO and continues: TVO has complied with the plant contract and valid nuclear safety methods and expects also Areva to do so. The schedule for the construction site is challenging and Areva's public speculation about stopping the works does not make it any easier to keep to it.
At present, total workforce on the site exceeds 4300. Works have proceeded during the summer, and the installation phase has now started also in some parts of the reactor building.
For further information, please contact:
Jarmo Tanhua, President and CEO, tel. +358 2 8381 2000
Jouni Silvennoinen, Senior Vice President, Project, tel. +358 2 8381 4100
Anna Lehtiranta, Senior Vice President, Corporate Relations, tel. +358 2 8381 5200.