2008
31.12.2008:
Olkiluoto 3 delay and related costs into arbitration
17.10.2008:
Start-up of Olkiluoto 3 may be postponed until 2012
26.08.2008:
The Finnish Construction Trade Union has given a notice for strike concerning the OL3 construction site
30.07.2008:
Small fire at Olkiluoto 3 construction site
24.06.2008:
Appointments in the TVO management
04.06.2008:
Outages at Olkiluoto completed
02.06.2008:
Olkiluoto 1 plant unit being started up
31.05.2008:
Reduced effect at Olkiluoto 2
14.05.2008:
Olkiluoto 2 annual outage completed
05.05.2008:
Annual outages started at Olkiluoto power plant
25.04.2008:
TVO filed today an application for a decision-in-principle concerning the construction of a new nuclear power plant unit at Olkiluoto
14.02.2008:
The EIA Report for the fourth nuclear power plant unit at Olkiluoto has been completed - The report was submitted today to the Ministry of Employment and the Economy
06.02.2008:
Extension of the warehouse and maintenance buildings reached roof-top height at Olkiluoto
22.01.2008:
CO2 capture system to be developed for Meri-Pori power plant in Finland
05.01.2008:
Production break at the Olkiluoto 2 unit
02.01.2008:
Production record at the Olkiluoto Nuclear Power Plant