Teollisuuden Voima Oyj’s Interim Report January 1–March 31, 2017

24.4.2017

​ During the first quarter of the year, Teollisuuden Voima's electricity generation at Olkiluoto 1 and 2 plant units continued safely and reliably. At Olkiluoto 3 EPR, the installation works and process system tests continued. Simulator training for OL3 operating personnel kicked off in February, enabling the completion of licensing training. Posiva’s encapsulation plant excavations will be completed during the spring.

Full TVO Interim Report January 1–March 31, 2017 (pdf)

Operating Environment

During the first quarter of the year, the use of electricity in Finland decreased by 3.1 percent compared to the corresponding period of the previous year.

The Ministry of Economic Affairs and Employment is preparing an amendment to the Nuclear Energy Act. The Act was circulated for comments during March–April, and after the parliamentary handling it is to enter into force as from the beginning of 2018. Changes will be made to meet the requirements of the directives adopted within the framework of EURATOM. In preparation for the Act, some change requirements related to national legislation, e.g. decommissioning of nuclear facilities, nuclear waste management, and safety arrangements have been examined.

A set of legislative measures on energy, so called “Clean Energy for all Europeans” package published by the European Commission in November 2016 has passed to the European Parliament and Council for consideration. From the nuclear industry’s perspective, the most relevant legislative proposals of the Clean Energy package are energy efficiency directive, renewable energy directive, electricity directive, and regulation on the governance of the Energy Union. The legislative process will take approximately two years.

Financial Performance

TVO operates on a cost-price principle (Mankala principle). TVO's goal is not to make profit or pay dividends. The shareholders are charged incurred costs on the price of electricity and thus in principle the profit/loss for the period under review is zero, unless specific circumstances dictate otherwise. The shareholders pay variable costs based on the volumes of energy supplied and fixed costs in proportion to their ownership, regardless of whether they have made any use of their share of the output or not. Because of the Company's operating principle, key indicators based on financial performance will not be presented.

The consolidated turnover for the period under review January 1–March 31, 2017 was EUR 82.4 (January 1–March 31, 2016: EUR 92.8 million). The amount of electricity delivered to shareholders was 3,827.5 (4,049.5) GWh. The lower delivery volume to shareholders was mainly due to lower delivery volume of Meri-Pori coal-fired power plant compared to the previous year.

The consolidated profit/loss was EUR -0.7 (6.3) million.

Financing and Liquidity

TVO's financial situation has developed as planned.

TVO's liabilities (non-current and current) at the end of the period under review, excluding the loan from the Finnish State Nuclear Waste Management Fund relent to shareholders, totaled EUR 4,413.2 (December 31, 2016: 4,521.8) million, of which EUR 479.3 (479.3) million were subordinated shareholder loans. During the period under review, TVO raised a total of EUR 100.0 (0.0) million in non-current liabilities. Repayments during the period under review amounted to EUR 160.7 (0.0) million.

In February 2016, TVO signed a new syndicated revolving credit facility of EUR 1.3 billion. The facility consists of two tranches: EUR 1,000 million 5-year tranche and EUR 300 million 3-year tranche. Both tranches included two one-year extension options, and in January 2017, both of them were extended by one year. In March 2017, TVO also signed bilateral revolving credit facilities totaling EUR 200 million. Both syndicated and bilateral facilities are undrawn.

The OL3 EPR project's share of financing costs has been capitalized in the balance sheet.

TVO uses its right to borrow funds back from the Finnish State Nuclear Waste Management Fund within the framework of legal regulations. On March 31, 2017 the amount of the loan was EUR 655.5 (December 31, 2016: 1,027.1) million and it has been relent to the Company's A-series shareholders. On March 31, 2017 loan from the Finnish State Nuclear Waste Management Fund was decreased by EUR 371.5 (March 31, 2016: increase 18.0) million.

Nuclear Power

Olkiluoto 1 and Olkiluoto 2

The electricity production of the Olkiluoto power plant units Olkiluoto 1 (OL1) and Olkiluoto 2 (OL2) during the period under review was 3,804 (3,882) GWh. The total load factor was 100.0 (100.0) %.

The plant units operated safely and reliably during the period under review. OL1’s net production was 1,886 (1,935) GWh and the load factor 99.5 (100.0) %. OL2’s net production was 1,918 (1,947) GWh and the load factor 100.0 (100.0) %.

Olkiluoto 1
Average electrical power MW
April 1, 2016–March 31, 2017


OL1_2016-04-01_2017-03-31_en.gif

Olkiluoto 2
Average electrical power MW
April 1, 2016–March 31, 2017


OL2_2016-04-01_2017-03-31_en.gif

On January 26, 2017 TVO filed with the Ministry of Economic Affairs and Employment an application for the renewal of the operating license of OL1 and OL2. The renewal of the operating license is applied for from the Government until the end of 2038. The 20-year operating license currently in force must be renewed by the end of 2018.

Olkiluoto 3 EPR

Olkiluoto 3 EPR (OL3 EPR), currently under construction, was procured as a fixed-price turnkey project from a consortium (Supplier) formed by AREVA GmbH, AREVA NP SAS and Siemens AG. As stipulated in the plant contract, the consortium companies have joint and several liability for the contractual obligations. According to the schedule last updated by the Supplier in September 2014, regular electricity production in the unit will commence at the end of 2018.

In 2016, Areva Group announced a restructuring of its business. The restructuring plan apparently involves a transfer of the operations of Areva NP, excluding the OL3 EPR project and certain other operations, to an ad hoc structure which is to be sold to EDF. On November 16, 2016, Areva and EDF announced that they had made a binding agreement on the restructuring, which was announced to be completed during the second semester of 2017. The implementation of the restructuring plan is subject to decisions and clearances, such as those related to the state aid and merger connected with the plan. In January 2017, the EU Commission made a conditional decision on the state aid, and after the reporting period, in April 2017, the Commission has received a merger control notification. TVO requires that the restructuring respects the completion of the OL3 EPR project within the current schedule and that all liabilities of the plant contract are respected.

Most of the construction works for the plant unit have been completed. The installation of the electrical systems, the instrumentation and control system (I&C), and mechanical systems is still in progress. Simulator training for the operating personnel commenced in February 2017.

The first phase of the commissioning of the turbine plant is completed. Some of the systems and components will be kept in operation; the rest has been preserved by the Supplier in accordance with a separate plan. In January 2017, de-preservation was started at the turbine plant.

The workforce at the site at the end of the period under review was about 2,400 persons. Occupational safety at the site remained at a good level.

The pending disputes concerning the plant unit are described in the paragraph ‘Pending Court Cases and Disputes’.

All realized costs of the OL3 EPR project that can be recognized in the cost of the asset have been entered as property, plant and equipment in the Group balance sheet.

Nuclear Fuel

During the period under review, nuclear fuel purchases amounted to EUR 15.2 (19.9) million and the amount consumed to EUR 14.0 (13.6) million.

The nuclear fuel and uranium stock carrying value on March 31, 2017 was EUR 232.2 (December 31, 2016: 231.0) million.

Nuclear Waste Management

Under the Finnish Nuclear Energy Act, the Company is responsible for the measures related to nuclear waste management and the related costs.

The liabilities in the consolidated financial statement show a provision related to nuclear waste management liability of EUR 958.9 (December 31, 2016: 954.6) million, calculated according to the international IFRS accounting principles. A corresponding amount, under assets, represents the Company’s share in the Finnish State Nuclear Waste Management Fund.

In order to cover the costs of nuclear waste management, TVO makes contributions to the Finnish State Nuclear Waste Management Fund. In December 2016, MEAE set TVO's liability for nuclear waste management at EUR 1,450.1 (1,369.4) million to the end of 2016 and the Company's funding target for 2017 at EUR 1,428.4 (1,369.4) million.

In March 2017, the Finnish State Nuclear Management Fund confirmed TVO’s nuclear waste man-agement fee for 2016 at EUR 49.1 (11.4) million, which was paid into the Fund on March 31, 2017 (March 31, 2016). The nuclear waste management fee for 2017 will be confirmed in March 2018.

Final Disposal of Spent Nuclear Fuel

Posiva Oy is in charge of executing in Olkiluoto the final disposal of the spent nuclear fuel generated by its owners, TVO at its power plant in Olkiluoto and Fortum at its power plant in Loviisa.

The excavation to prepare the ground for the encapsulation plant started in November 2016 and the second phase of work in the ventilation building have progressed according to plans. The excavation work at the final disposal facility itself was launched in December 2016 and is progressing according to plan with the excavation of the first shaft connections of the canister shaft and the vehicle access tunnels leading to the final disposal facility. The excavation work is estimated to take two and a half years.

At the end of March, Posiva’s owners submitted the Nuclear Waste Management Annual Report for 2016 to the Ministry of Economic Affairs and Employment.

Coal Power

Meri-Pori

The amount of electricity produced by TVO’s share at the Meri-Pori coal-fired power plant on January 1–March 31, 2017 was 29.3 (173.8) GWh requiring 10.1 (61.7) thousand tons of coal and 24.3 (147.4) thousand tons of carbon dioxide emission rights.

TVO’s share of Meri-Pori’s production
Average electrical power MW
April 1, 2016–March 31, 2017


Meri-Pori_2016-04-01_2017-03-31_en.gif

Acquisitions of Tangible and Intangible Assets and Shares

Investments during the period under review were EUR 67.7 (63.4) million. Investments of the parent company were EUR 66.3 (61.8) million, of which EUR 55.2 (58.2) million were allocated to the OL3 project.

At present, several plant modifications are planned and implemented in Olkiluoto to prepare the OL1 and OL2 plant units for the renewal of the operating license in 2018.

During the period under review, emission rights were acquired worth EUR 0.1 (0.8) million. The Company's need for carbon dioxide emission rights for the period under review are covered by acquired emission rights.

Pending Court Cases and Disputes

In 2012, TVO submitted a claim and defence in the International Chamber of Commerce (ICC) arbitration proceedings concerning the delay and the ensuing costs incurred at the Olkiluoto 3 EPR project. In July 2015, TVO updated its quantification estimate of its costs and losses to amount to approximately EUR 2.6 billion until December 2018, which, according to the schedule submitted by the OL3 Supplier in September 2014, is the estimated start of regular electricity production of OL3.

The proceedings were initiated in December 2008 by the OL3 Supplier. The Supplier’s monetary claim, as updated in February 2016, was approximately EUR 3.52 billion in total. The sum was based on the Supplier’s updated analysis of events that occurred through September 2014, with certain claims quantified to December 31, 2014. The sum included penalty interest (calculated to June 30, 2016) and payments allegedly delayed by TVO under the plant contract amounting to a combined total of approximately EUR 1.45 billion, as well as approximately EUR 135 million in alleged loss of profit.

In November 2016, the ICC Tribunal made a final and binding partial award. In the partial award, the ICC Tribunal addressed the early period of the project (time schedule, licensing and licensability, and system design). This comprised many of the facts and matters that TVO relies upon in its main claims against the Supplier, as well as certain key matters that the Supplier relies upon in its claims against TVO. In doing so, the partial award finally resolved the great majority of these facts and matters in favour of TVO, and conversely rejected the great majority of the Supplier’s contentions in this regard. The partial award did not take a position on the claimed monetary amounts. The arbitration proceeding is still going on with further partial awards to come before the final award where the Tribunal will declare liabilities to pay compensation.

TVO considers its claims to be well-founded and has considered and found the claims of the Supplier to be without merit. The partial award provides material confirmation for this position.

TVO has sought to obtain more detailed information from Areva Group on its announced restructuring and its impacts on the OL3 EPR project. As TVO has not received such information it begun legal proceedings at the end of September 2016 before the Commercial Court of Nanterre in France. The aim of this is to urgently obtain this information with a view to securing the assurances that all the necessary financial and other resources, particularly in relation to the EPR technology capabilities, will be allocated for the completion and long-term operation of OL3 EPR and that the Supplier Areva-Siemens will meet all their contractual obligations and liabilities.

The Supplier consortium companies (AREVA GmbH, AREVA NP SAS and Siemens AG) are jointly and severally liable for the plant contract obligations.

TVO has not recorded any receivables or provisions on the basis of claims presented in the arbitration proceedings.

Personnel

The total number of personnel in the Group at the end of the period under review was 759 (December 31, 2016: 747, March 31, 2016: 753). The number of permanent employees in the Group at the end of the period under review was 740 (December 31, 2016: 721, March 31, 2016: 732).

To support the commissioning of OL3 EPR, a major recruitment campaign was launched in the beginning of the year. The organization will be strengthened with some twenty technical experts. The persons to be recruited will start their work primarily in Engineering and Expert Services, Safety and Security Services or Electricity Production.

The simulator training for OL3 operating personnel and shift supervisors commenced in February with normal operation training (21 days/shift). Each shift will be given a total of 45 days of training in the simulator. OL3 plant knowledge training is given to the personnel in different ways in cooperation with the Supplier.

The collective agreements for different groups of personnel in the energy industry were in force in accordance with the so called framework agreement of labor confederations until January 31, 2018.

Annual General Meeting

TVO's Annual General Meeting on March 31, 2017 approved the financial statements for 2016, confirmed the consolidated income statement and balance sheet, and discharged the members of the Board of Directors and the President and CEO from liability.

Eight Board members were re-elected. Two new members, Esa Kaikkonen and Anders Renvall, were elected to the Board. At its organization meeting, the Board elected Lauri Virkkunen as Chairman and Matti Ruotsala as Deputy Chairman. The Board also chose from among its members the members and chairmen of the Board Committees.

Auditing

The Interim Report is unaudited.

Risks and Uncertainty Factors in the Near Future


The major risks and uncertainty factors in TVO’s operations have been presented in the 2016 Report of the Board of Directors.

During the period under review, no remarkable new risks connected with the Company’s operation have arisen.

Assessment of Year-End Developments

Electricity production is expected to continue as in previous years. The prerequisites for nuclear power production at Olkiluoto are good. Nuclear fuel availability is guaranteed by long-term agreements.

Realization of the OL3 EPR nuclear power plant project and preparing the plant unit for production will be continued. Testing of the process systems continue, and the next important milestone is the cold functional testing scheduled to commence next summer. TVO will continue to support the Supplier to complete the project.

The Meri-Pori coal-fired power plant capacity will be used in accordance with the former principles. Fortum’s share of the Meri-Pori power plant has been accepted into the reserve capacity, and TVO is examining the use of its own share in the future.

Posiva’s encapsulation plant excavations will be completed during the spring. The ongoing second phase works of the ventilation building will be completed during summer 2017.

Events after the Period under Review

No major events have taken place after the end of the interim report period.

April 24, 2017

Teollisuuden Voima Oyj
Board of Directors

For more information, please contact
Jarmo Tanhua, President and CEO, Tel. +358 2 8381 2000
Anja Ussa, Senior Vice President, Finance, Tel. +358 2 8381 6100